Remedial works are required at a number of new high-rise developments in Dublin.
An investigation is underway into construction problems at the €300 million Google site at Bolands Mills.
Developers have reported so-called "issues" to local representatives.
Labour Senator Kevin Humphreys wants Dublin City Council officals to visit the site to ascertain what exactly the problem is.
He said " We have to make sure that any buildings that go up in our city are of high quality and they are not a risk in the future either to the staff that are there or residents that would be living in these apartment blocks."
Issues With Concrete
Elsewhere, developers of the Salesforce offices at Spencer Dock have confirmed that they experienced problems with the concrete used during construction.
The Sunday Business Post reports the problem could have affected the building's lift shafts if it had gone undetected.
Developers have said the issue was discovered at an early stage and has been properly addressed.